The Bay Area embodied carbon community
Berkeley Way Apartments, on the east side, provides affordable housing for families (89 studios, one and two bedroom apartments) with community spaces, a common laundry room, and administrative offices. The Berkeley Food and Housing Project (BFHP) Hope Center, on the west side, includes a veterans transitional housing dormitory, 53 permanent supportive apartments for formerly unhoused people, and temporary sleeping accommodations. The ground floor offers a variety of services including a commercial kitchen, multipurpose room with multiple meal services and supportive programs, 24-hour reception, as well as supportive services, management, and administrative functions. The estimated cost of the entire development is approximately
$70M. The project broke ground in July 2020 and construction is anticipated to be complete in May 2022.
Berkeley Way
The Concrete
Berkeley Way is 4 stories of wood construction over two levels of prestressed concrete podium and a mat slab foundation. The total
amount of concrete on the project is approximately 4,000 cubic yards. From the start of the project, the team opted to specify cement content limits and sought to push for the lowest cement content possible. The mixes provided by Central and approved by TSE to date contain 55% less cement than national average concrete for the same strength. As a result, 614 metric tons CO2 equivalent of greenhouse gas emissions throughout the supply chain of the concrete will be avoided compared to a national average.
The Process
Key to the project success was initiating discussion with the concrete contractor early on to find mixes that achieved lower cement content without cost increase or time delay. During Construction Documents the team held meetings with the General Contractor, the concrete supplier, the structural engineer and Arup to analyze concrete mixes. They aimed for mixes with high cement replacements that would work structurally without adding significant time or cost. Having the team approach this together before the GMP process was helpful and got the team on the same page about goals.
During construction, there were multiple, last minute substitution requests. Some were due to seasonal fly ash shortages whereas others were to make the concrete pours simpler for the contractor. The former was dealt with by using mixes with slag only to replace cement instead of mixes with both fly ash and slag, which can have even lower cement. The latter was discussed by the design and construction teams before coming to an agreement on allowances that gave the contractor flexibility while still achieving high overall cement reduction targets. Throughout the submittal and substitution request process, the team needed to review the changes quickly, so the detailed tracking of the different mixes being used throughout different elements in the building, that Arup kept up to date, was essential.